ADR 0002: Roadmap threads, milestones and identifiers

  • Status: Proposed; merging the pull request that carries this ADR records acceptance
  • Date: 2026-10-08
  • Owners: Roadmap owner (@fmuia) with the dev meeting
  • Scope: the structure of roadmap/, its identifiers and its work board; no package code

Decision summary

  1. Domain threads replace activity workstreams. The roadmap is organised by who carries the work, not by the kind of activity: Technical development, Agentic integration and governance, Business development and reach (proposed), and Lab operations and access. Each thread has one accountable owner and serves named outcomes.
  2. Milestones are conditions, not phases. Each thread declares milestones with their own completion tests. A milestone counts as reached only when the board snapshot shows its items done. Its position on a thread page is the owner's intended path; it is never a date, a sprint or a phase.
  3. Outcomes are data. The vision statement and each outcome (title, statement, completion test, gaps closed) live in roadmap.toml, so the renderer can show, per thread, the path from today to the outcomes it serves and the evidence-backed progress along it.
  4. Thread-prefixed identifiers. Items are TECH-01, AI-01, BIZ-01, OPS-01; decisions are DEC-01 and up. Every migrated item and decision keeps its 2026-09 id as legacy_id, and the renderer emits it as an alias anchor, so existing links resolve. No id is ever reused.
  5. ClickUp is the work board (DEC-22, recorded 2026-10-08: proposed by Krishn and agreed by the roadmap owner and organization admins; workspace HSSM Ecosystem, Free plan). Git owns intent; ClickUp owns live state; no field is owned by both. The adapter is specified in plans/roadmap-threads-and-clickup-sync.md.

Why

The six workstreams of the 2026-09 roadmap mixed two axes: four were kinds of activity (Stabilize, Deliver, Verify, Throughput) and two were domains (Connect, Access and navigation). Nobody could own "Stabilize" across every domain, so the question of who owns each workstream stayed open; the vision and outcomes were written by domain and could not be rendered against the workstreams; and the marketing and business-development proposals of 2026-09-30 had no place in the scheme at all. The stakeholder review of 2026-09-29 had already removed horizons and the critical path because hand-set stages go stale; milestones defined as evidence-tested conditions keep that decision intact while giving each thread a readable path.

Consequences

  • Links by former id keep working through alias anchors; links by file name (roadmap/items/A1-…) break, and none exist outside the roadmap.
  • The weekly-report index on the open report branches (.claude/skills/dev-weekly-report/roadmap_index.py) accepts only ids matching [A-Z][0-9]{1,3}. It must accept [A-Z]{2,5}-[0-9]{2,3} before those branches merge, or the deck will group no roadmap items.
  • Threads marked adoption = "proposed" and their outcomes await the dev meeting under DEC-18; their milestones may be empty until then.
  • The generated pages gain one page per thread under roadmap/threads/.

Identifier map

Former New Thread Milestone
A1 TECH-01 Technical development Stable
A2 TECH-02 Technical development Stable
A3 TECH-03 Technical development Stable
A4 TECH-04 Technical development Stable
A6 TECH-05 Technical development Stable
A8 TECH-06 Technical development Stable
A7 TECH-07 Technical development Released
B3 TECH-08 Technical development Released
B4 TECH-09 Technical development Released
B1 TECH-10 Technical development Complete model surface
B2 TECH-11 Technical development Complete model surface
B6 TECH-12 Technical development Complete model surface
B7 TECH-13 Technical development Complete model surface
B8 TECH-14 Technical development Complete model surface
B9 TECH-15 Technical development Complete model surface
B10 TECH-16 Technical development Complete model surface
C1 TECH-17 Technical development Trustworthy artifacts
C2 TECH-18 Technical development Trustworthy artifacts
C3 TECH-19 Technical development Trustworthy artifacts
C4 TECH-20 Technical development Trustworthy artifacts
C6 TECH-21 Technical development Trustworthy artifacts
B5 TECH-22 Technical development Trustworthy artifacts
B11 TECH-23 Technical development Trustworthy artifacts
E1 AI-01 Agentic integration and governance Proposed
E6 AI-02 Agentic integration and governance Proposed
E7 AI-03 Agentic integration and governance Proposed
A5 AI-04 Agentic integration and governance Proposed
C5 AI-05 Agentic integration and governance Proposed
E2 AI-06 Agentic integration and governance Shadow
E4 AI-07 Agentic integration and governance Shadow
D2 AI-08 Agentic integration and governance Shadow
— (new) AI-09 Agentic integration and governance Shadow
E3 AI-10 Agentic integration and governance Live behind approvals
E5 AI-11 Agentic integration and governance Live behind approvals
F1 OPS-01 Lab operations and access Reachable
F2 OPS-02 Lab operations and access Reachable
F3 OPS-03 Lab operations and access Reachable
F4 OPS-04 Lab operations and access Reachable
F5 OPS-05 Lab operations and access Reachable
D1 OPS-06 Lab operations and access Governed delivery
D3 OPS-07 Lab operations and access Governed delivery
D4 OPS-08 Lab operations and access Governed delivery
D5 OPS-09 Lab operations and access Governed delivery
D6 OPS-10 Lab operations and access Governed delivery
D7 OPS-11 Lab operations and access Governed delivery
F6 OPS-12 Lab operations and access Navigable
F7 OPS-13 Lab operations and access Navigable
F8 OPS-14 Lab operations and access Navigable
F9 OPS-15 Lab operations and access Navigable
F10 OPS-16 Lab operations and access Navigable

Decisions D-01 through D-22 became DEC-01 through DEC-22 with the same numbers.